So, it's been a while, and in response to those hundreds of requests for an update here's the next installment.
A lot has happened over the past few weeks: Paulioni has been over from der Nedderlandss, the kids have been on school holiday, there's been a wedding anniversary, Camp Bestival, boat trips on the Thames and Wey Navigations (ahoy there Captain Trievnor!) and in fact, some work has also been done on the extension .........
| "Ehh, I'll come later, I'm busy!" |
![]() |
| Ready to start work Where is everyone? |
Just to recap, the middle of August saw most of the ground floor brickwork complete, per the following photos:
![]() |
| Back Wall |
![]() |
| Front Wall |
| Checkout the missing bricks ... |
![]() |
| View from 'Fredo's Bedroom |
![]() |
| Padstones |
![]() |
| And another one |
On a number of occasions, I've been told that getting the beams up without a crane will be "un pezzo di torta" - but since they weigh in at around 180Kg each I'm not so sure, hmmmm.....we'll see ..........
![]() |
| So where's the crane then? |
The great news is that Rafaelle is coming over to help tomorrow - I'm feeling better already because he could probably lift a beam with one hand ..........!
![]() |
| errr, use this .... |
We also have a Genie Lift for the weekend, capable of lifting each beam up. Will be a little bit tricky but it's ok apparently.Anyway, Lucia isn't too worried ....
If I survive "Steel Beam Day", watch out for another post coming your way soon!